    Scope of Work:
    This is our most complicated project because we are going to add about 97,000 SF of new building and renovate approximately 14,400 sf while the school is occupied. We will be adding two story structures along the front and along the right side of the existing campus.  
    Building "C" was completed in August 2015, Building "A" was also completed in October 2015, and Building "B" is estimated to be completed in March 2016, Demolition of Buildings 300, 500, 600 and portions of 200 will occur over the summer as well as the completion of the new bus loop. 
    • Scope for New Construction:  97,249 Total Sq. Ft.
    • Scope for Renovations: 14,424 + Total Sq. Ft.
    • Approved Construction Budget: $26,566,399.00
    • Start Date: 3 June 2014
    • Estimated Date of Completion: August 2016
    • Anticipated Student Population: 2,100 
     
    The Architect selected for the Project:  
    SGA Logo  
    SGA Architecture         
     
    Don Baus, President N. Charleston Division
    Land Planning | Landscape Architecture | Architecture | Interior Design
    1535 Hobby Street; Suite 204; North Charleston, SC  29405
    Phone  843.853.4506
     
    The Contractor selected for the Project:  
     Thompson Turner Logo
     
    Todd McElveen
    100 North Main Street
    Sumter, South Carolina 29150
    Office: 803-418-8231 (Direct)